Project assurance report · illustrative sample

Northbridge Data Centre Exit (illustrative)

March 2026 · Evidence as of 20 Mar 2026 · 6 documents · 19 findings

Executive summary

2 critical and 10 high-priority findings need attention on Northbridge Data Centre Exit (illustrative).

Most material: 1 open risk is scored at critical exposure; Readiness is reported as achieved, but 4 readiness criteria are still open; 1 dependency has no accountable owner.

7 findings are based on documents that contradict each other — each shows both sides with their sources.

Calculated delivery confidence is 40/100 (guarded); see the methodology for its inputs.

Generated directly from the findings below.

2 critical10 high6 medium1 low

Critical

2

findings

High

10

findings

Conflicts

7

between documents

Overdue actions

5

of 6 open

Milestones at risk

5

of 7 dated

Milestones

Feb 26Mar 26Apr 26evidence dateM-1 Hosting contract signed — baseline 16 Jan 2026, forecast 16 Jan 2026M-1 Hosting con…M-2 Landing zone build complete — baseline 13 Feb 2026, forecast 20 Feb 2026, +7 daysM-2 Landing zon…M-3 Wave 1 application migration — baseline 6 Mar 2026, forecast 13 Mar 2026, +7 daysM-3 Wave 1 appl…M-4 Data migration rehearsal complete — baseline 27 Mar 2026, forecast 27 Mar 2026 — sources disagreeM-4 Data migrat…≠M-5 Operational acceptance — baseline 10 Apr 2026, forecast 10 Apr 2026 — sources disagreeM-5 Operational…≠M-6 Wave 2 cutover — baseline 24 Apr 2026, forecast 24 Apr 2026 — sources disagreeM-6 Wave 2 cuto…≠

Findings

Ranked by materiality and evidence quality. Each shows its sources.

What was found
R-1 “Vendor cannot provide data extract in the agreed format” (L4 × I5 = 20).
Why it matters
Risks at this level are, on the project’s own scoring, both likely and severe. They warrant explicit governance attention and contingency.
Severity rationale
Likelihood × impact of 20 or more on a 5 × 5 scale, as scored in the source register.
Suggested next action
Confirm each has an owner, a funded mitigation and a contingency, and that it is on the next steering committee agenda.

Evidence

RAID Log 2026-03-13.csv · row 2as of 13 Mar 2026

States: L4 × I5

ID: R-1 | Type: Risk | Description: Vendor cannot provide data extract in the agreed format | Workstream: Data | Owner: P. Nair | Likelihood: 4 | Impact: 5 | Status: Open | Mitigation / Response: Weekly format review with vendor; A-7 to agree schema
Uncertainty: Scores are the project’s own. Uozan has not re-scored the risks.
What was found
1 statement in reporting documents claim readiness, while the readiness evidence shows OR-2 “Monitoring and alerting configured for migrated services” in progress; OR-3 “DR test passed” open; OR-4 “Runbooks accepted by operations” open; OR-5 “Service catalogue updated” open.
Why it matters
Going live on an unsupported readiness claim is a primary cause of service-transition incidents.
Severity rationale
A governance-level claim directly contradicted by the criteria it depends on.
Suggested next action
Do not rely on the readiness claim until every criterion is evidenced and signed off by the receiving service owner.

Evidence — the sources disagree

This source

Programme Status Report - March 2026.txt · § “PROGRAMME STATUS REPORT”as of 18 Mar 2026

States: readiness claimed

Executive summary The programme remains on track. Wave 1 migration has been delivered and the service is operationally ready for go-live of Wave 2 as planned. Data migration rehearsal remains on track for the end of March.

Conflicting source

Operational Readiness Checklist 2026-03-16.csv · row 3as of 16 Mar 2026

States: In progress

ID: OR-2 | Readiness criterion: Monitoring and alerting configured for migrated services | Status: In progress | Due Date: 2026-03-20
Operational Readiness Checklist 2026-03-16.csv · row 4as of 16 Mar 2026

States: Not started

ID: OR-3 | Readiness criterion: DR test passed | Owner: K. Duffy | Status: Not started | Due Date: 2026-04-03
Operational Readiness Checklist 2026-03-16.csv · row 5as of 16 Mar 2026

States: Open

ID: OR-4 | Readiness criterion: Runbooks accepted by operations | Owner: T. Walsh | Status: Open | Due Date: 2026-03-27
Operational Readiness Checklist 2026-03-16.csv · row 6as of 16 Mar 2026

States: Not started

ID: OR-5 | Readiness criterion: Service catalogue updated | Status: Not started | Due Date: 2026-04-15
Uncertainty: The claim is matched by wording. Read the quoted passage to confirm it refers to the same release or service.

Risk analysis

As scored in the project’s own registers. Uozan does not re-score risks.

Likelihood
5
4
1
1
3
1
2
1
1
12345

Impact

Risk heatmap. 1 at likelihood 4, impact 5; 1 at likelihood 4, impact 4; 1 at likelihood 3, impact 5; 1 at likelihood 2, impact 3

Open risks

4

5 in registers

High exposure

3

likelihood × impact ≥ 15

Without an owner

2

open risks

Scored

4

with likelihood and impact

Concentration by workstream

WorkstreamOpen risksHighest exposure
Data1max 20
Migration1max 16
Service Transition1max 15
Commercial1max 6

Milestones and schedule

Baseline against the most recent forecast or actual. Where documents disagree, the milestone is marked.

BaselineForecastCompleteSlipped / at riskLate or sources disagree≠Conflicting dates
Feb 26Mar 26Apr 26May 26Jun 26Jul 26Aug 26evidence dateM-1 Hosting contract signed — baseline 16 Jan 2026, forecast 16 Jan 2026M-1 Hosting contract signedM-2 Landing zone build complete — baseline 13 Feb 2026, forecast 20 Feb 2026, +7 daysM-2 Landing zone build completeM-3 Wave 1 application migration — baseline 6 Mar 2026, forecast 13 Mar 2026, +7 daysM-3 Wave 1 application migrationM-4 Data migration rehearsal complete — baseline 27 Mar 2026, forecast 27 Mar 2026 — sources disagreeM-4 Data migration rehearsal comp…≠M-5 Operational acceptance — baseline 10 Apr 2026, forecast 10 Apr 2026 — sources disagreeM-5 Operational acceptance≠M-6 Wave 2 cutover — baseline 24 Apr 2026, forecast 24 Apr 2026 — sources disagreeM-6 Wave 2 cutover≠M-7 Legacy data centre decommissioned — baseline 30 Jun 2026, forecast 31 Jul 2026, +31 days — sources disagreeM-7 Legacy data centre decommissi…≠
MilestoneBaselineForecast / actualSlipStatusSources
M-1Hosting contract signed16 Jan 202616 Jan 20260dcompleteSingle source
M-2Landing zone build complete13 Feb 202620 Feb 2026+7doff trackSingle source
M-3Wave 1 application migration6 Mar 202613 Mar 2026+7dcomplete2 agree
M-4Data migration rehearsal complete27 Mar 202627 Mar 20260don trackDisagree
M-5Operational acceptance10 Apr 202610 Apr 20260don trackDisagree
M-6Wave 2 cutover24 Apr 202624 Apr 20260don trackDisagree
M-7Legacy data centre decommissioned30 Jun 202631 Jul 2026+31don trackDisagree

Critical-path analysis is not performed: it needs task-level logic links that status documents rarely contain.

Actions and accountability

Current state of each action, taken from the most recent document that mentions it.

Open

6

Overdue

5

No owner

2

No due date

0

Re-dated / deferred

0

Complete

0

Dependencies and blockers

Links stated in the documents (dependency columns, “depends on M4”, “mitigated by A-9”).

milestone: M-1M-1milestone: M-2M-2milestone: M-3M-3milestone: M-4 — referenced by a findingM-4milestone: M-5 — referenced by a findingM-5milestone: M-6 — referenced by a findingM-6milestone: M-7 — referenced by a findingM-7risk: R-1 — referenced by a findingR-1risk: R-3 — referenced by a findingR-3action: A-7 — referenced by a findingA-7action: A-9 — referenced by a findingA-9dependency: D-2 — referenced by a findingD-2

Arrows point from an item to what it depends on. Amber outline = referenced by a finding. Bar colour: blue dependency, grey milestone, orange risk.

Financial analysis

Deterministic arithmetic on figures stated in the documents. Missing figures are never estimated.

Budget

€2.55m

lines with budget & forecast

Forecast

€2.90m

Variance

+€350k

13.7% of budget

Actual to date

€1.43m

Hosting and network+€50k (+4.2%)
Migration services+€180k (+20%)
Dual running+€120k (+40%)
Contingency€0 (0%)
Actual to dateBudgetForecast (over budget)

Sources and coverage

What each document contributed. Types and dates are detected automatically; they can be corrected on the project page.

DocumentDetected typeAs ofPassagesItemsExtraction
Integrated Plan v3 2026-02-02.csvPlan / schedule2 Feb 202677complete
RAID Log 2026-03-13.csvRAID log13 Mar 20261313complete
Steering Committee Minutes 2026-03-11.txtMeeting minutes11 Mar 202694complete
Programme Status Report - March 2026.txtStatus report18 Mar 2026137complete
Budget Tracker 2026-03-01.csvFinancial1 Mar 202644complete
Operational Readiness Checklist 2026-03-16.csvReadiness checklist16 Mar 202655complete

Methodology and limitations

How this report was produced

  1. Text, tables and metadata were extracted from each document with their location (page, sheet and row, section, slide).
  2. Structured registers were mapped to risks, actions, milestones, dependencies, decisions and budget lines by column. Narrative text was read by an AI model; an item was kept only if its quoted words and values appear verbatim in the source.
  3. Items were matched across documents on shared IDs or strong title matches. Ambiguous matches were left separate.
  4. Deterministic rules compared dates, statuses, owners and figures, taking each document’s date into account so that a newer document superseding an older one is not, on its own, treated as an error.
  5. Findings were ranked by severity and evidence quality.

Delivery confidence — inputs

IndicatorEvidenceWeightScore
Milestones on schedule

Complete, or not late, not red and not slipped more than 14 days against baseline.

5 of 735%71
Open actions within date

Open actions whose due date has not passed.

1 of 620%17
Risks below high exposure and owned

Open risks scored below 15 (L × I) with a named owner.

1 of 425%25
Cross-document consistency

Items that appear in more than one document without a high-severity conflict.

3 of 820%38

4 of 4 indicators had enough data; weights re-normalised over those. Rounded to the nearest 5. Capped at 55 because at least one critical finding is open. This is a calculated indicator of evidence health, not a forecast.

What each finding rests on

Stated in sourceCalculatedSources conflictInference — verifyMissing evidence
  • Findings are derived only from the documents uploaded. Information held elsewhere is not visible to the analysis.
  • This is decision support for a project professional. It is not an independent audit, has not been approved by any governance body, and does not guarantee correctness. Verify material findings against the cited sources before acting.